Upper South Boulder Creek Status

We have selected a contractor Team Flywater and Walsh.

Conceptual Design Document link is posted on the website

Next steps – Finalize contract – preparation for permitting and finalizing desing

Construction should really get rolling in September.

Volunteer needs – probably minimal this year – may need some replanting of willows in harvest areas. Next spring – reseeding and more planting.  Will provide more details later.

South Boulder Creek pre-bid meeting

On May 14th we met with potential bidders to discuss improvements to upper South Boulder Creek.  There were approximately 10 potential bidders along with representatives from Colorado DOW, U.S. Forest Service, Denver Water Board and Boulder Flycasters.  We spent about 1.5 hours on bid details and over two hours looking at the improvement sites.  Next steps are:

Proposals due 6/14

Contractor selection – 7/1

Begin Construction – 8/1