BFC Rogers Park Project Meeting
November 6, 2006
ATTENDEES: Al Permut, Roger Svendsen, Dave Blauch (via phone), Hillary Browning
(ERC Rep for Dave), Paul Prentiss, Dave Clark, Bob Bush, Mark Riley
Old Business:
- DOW Habitat Stamp Grants: At the 7/24 project meeting it was agreed
that we should apply for grant money from this source. The schedule was
very tight … application deadline 7/31. The BFC board approved an
expenditure of $5000 on 7/26 to fund ERC for the project design work described
in the ERC proposal dated 6/27/06. ERC performed a stream survey on 7/27
and prepared a conceptual design suitable for the grant application. Input
was provided to Dave Nickum, Director of Colorado Trout Unlimited, CTU,
who completed the application and associated documentation. (Thanks
Dave!) The project is currently estimated to cost $215K. We requested
$160K from grant funds with the balance to be obtained through "in-kind"
funding and/or additional grant funds. The Habitat Stamp funds will be
made available in 2007. The awarding of grants was scheduled for late October,
however just prior to this meeting, Dave Nickum informed Paul Prentiss
that the award schedule has slipped until mid-November. At this meeting,
there was some discussion about the probability of winning this grant.
Though 60% of Habitat Stamp funds come from anglers vs. 40% from hunters,
it is suspected that most grant money will be used for hunting habitat
improvements. It was speculated that state income is greater from the hunting
community vs. anglers, hence the skew of awards in their direction. Dave
Nickum, according to Paul, has said he will request an explanation if most
of the grant money is directed toward hunting organizations.
- Conceptual Design Discussion: Note: Dave Blauch
was planning to attend this meeting, however he was called away to a project
in Montrose, CO and had one of his employees, Hillary Browning, represent
him at this meeting. Dave called in at 7:45 P.M. to field questions that
Hillary had not answered earlier. Hillary distributed an 11” X 17” color
view of the suggested changes to the project area. This document shows
a project length of 2000 feet and recommended areas for low flow channel
improvements, riffle-pool sequences, major and minor bank stabilization,
in-stream habitat features, and areas for improved public access points.
The following is a summary of discussion topics and suggestions:
- Al suggested that minimal stream access improvements were necessary
in his opinion. It was generally agreed that this was the case. Hillary
will carry that message to Dave for further discussion. Adding one
access point in the approximate middle of the project might be good.
- Parking was discussed briefly. Conversation with both CDOT and the
County Sheriff’s Dept. is important. The CDOT discussion can
be initiated when a meeting with Mark G. from CDOT takes place. Design
and funding for parking improvements has not yet been addressed. It
was suggested that CDOT had the expertise in this area, as well as
ownership, and therefore should be asked to perform this work.
- With Dave on the phone, a question was asked for a definition of “in-stream
habitat features”. Dave said they are usually boulder clusters.
- Dave explained that boulders would be buried upstream where channels
are re-graded in order to maintain stream characteristics.
- Al asked if the “straight” portion of the stream could
be changed to meander away from the road. This was viewed positively
by the group and Dave will consider this change. There will probably
be a cost impact, however such a change might be worth the extra expense.
- Dave explained the difference between major and minor bank stabilization.
Major stabilization includes boulders as well as vegetation. Minor
stabilization only requires vegetation.
New Business:
- Additional Grant Funding: Paul mentioned that funds may be available
from the TU "Embrace a Stream" program. Up to $10,000 is available. The
deadline for a letter stating the intent of submitting an application is
November 20. The actual application is due by December 18. These funds
are made available in 2007 if awarded. The committee elected to submit
a letter of intent and file an application. Paul will write the letter
and Al will assist with the completion of an application.
The next meeting will be scheduled after we learn the status of our Habitat
Stamp funding request.
The meeting concluded about 8:30 PM.
Return to Rogers Park page