Rogers Park Restoration Committee Meeting Minutes
Monday July 24, 2006
Attendees: Paul Prentiss, Bob Bush, Michael Stein, Mark Riley, Dave Blauch,
Dave Clark, Roger Svendsen, Dave Steinman
- Meeting was held at Roger’s home and was called to order by Roger
at 7:10 P.M.
- Review ERC Proposal - Roger reviewed the comments he has received regarding
the ERC Proposal. They included: Concern over BFC single sourcing project,
Limited Grant Funding Sources, Project schedule impact due to Fishing is
Fun grant money not available until the Spring of 2008, and funding the
project as a design/build, versus requesting separate proposals for each
phase.
- BFC Single Sourcing Project to Ecological Resource Consultants, Inc.
(ERC) - The group discussed the fact that this approach flowed naturally
from previous meetings. During earlier meetings, Dave Blauch described
the work his company has done and provided a large number of references.
Examples of work product were shown to several committee members and
were well received. ERC provided a number of references, some of them
from TU clients, and all were extremely pleased with ERC’s work.
Based on these facts and other positive attributes, the committee decided
to continue to recommend to the BFC Board of Directors that ERC be
awarded funds ($5K) to perform the first phase of the project. It was
noted that obtaining additional bids would require significant effort
in the preparation of a Request for Proposal document, along with Proposal
scoring documentation. It would significantly impact our schedule at
this point. Our approach to this project does not mean that all future
projects will be approached in this manner. It should also be noted
that if the ERC budget estimate for the construction phase of the project
is deemed to be too high by the committee, our relationship with ERC
can be terminated and the retail value of the first phase of the project
(an additional $15K) will be paid to ERC. The construction phase would
then be awarded to another company. Another minor concern is a comment
Al Permut and Roger heard from the County. The two people we talked
with had not experienced a project where competitive bids had not been
required. Those were all dealing with County funds. We discussed this
risk and determined it was zero or at best minimal. We are not using
County funds, and in fact several meeting attendees are aware of existing
and previous situations where the county has not required bids for
County projects. Roger and Al will continue to request acceptance on
this point from the County.
- Limited Grant Funding Sources - Roger and Paul explained an opportunity
to obtain earlier funding from the Colorado Dept. of Wildlife Habitat
Stamp Fund. The application for these funds must be submitted by 7/31/06,
but after reviewing the requirements, the committee decided to work
hard and meet the deadline. The application requires letters of support
from the City of Boulder, Boulder County, and CDOT. Rog will work to
get those letters completed and sent to Paul. We also need a design
concept document and high level budget. Dave will prepare those items
beginning immediately after the Board grants funding for his proposal.
Dave Nickum, CTU, has agreed to pull all of this information together
and Paul will assure Dave has everything he needs. This funding would
be available next year, 2007, which would allow us to complete construction
in the Fall of 2007 and the vegetation portion in the Spring of 2008.
- Design/Build Contract vs. Separate Contracts - This topic was discussed
and it was decided to go forward with a Design/Build approach. The
cost of construction will be reviewed after design is complete to assure
it is competitive. Our risk is considered low using this approach and
ERC’s cost and budget track record is excellent.
- Review ERC References - All references were either positive or extremely
positive, with some ERC work leading to follow-on business which is one
of the best possible recommendations.
- Decide on need for additional proposals - This topic was also discussed.
Nobody present thought this would be a good idea or necessary. Refer to
the discussion above.
- Review CDOT Phone Conversation (Mark Goselin - 303-442-5640) - Roger
spoke with Mark several weeks ago. Mark asked that we not meet until the
design was well underway. At that time, he would like to meet with members
of the project team on the creek. He thought that based on our work at
the BFC park above the tunnel and the work we propose, approval from CDOT
will be a formality.
- Determine remaining requirements for BFC Board approval to release funds.
- In discussion, it was felt that the BFC Board of Directors will not have
any remaining concerns about going forward with ERC and their proposal.
Paul will notify Dave Blauch immediately after the meeting and if the contract
is approved, ERC will begin work on the design early Thursday morning and
will have documentation and budget estimates ready by Friday for submission
to the DOW for the Habitat Stamp grant.
- List Next Steps:
- Preliminary Design
- Permit Process
- Grant Funding
- Enlist Volunteers as needed - No additional volunteers are needed at
this time.
- Set next meeting date - Roger asked Dave Blauch to review his design
plan schedule and e-mail the group suggesting a date for our next meeting.
He will circulate design and/or other documents via e-mail prior to the
meeting.
- The meeting adjourned shortly after 8 P.M.
Respectfully Submitted,
Roger Svendsen
Return to Rogers Park page